ARC Residences Construction Update
Arc Residences, Toowong
November Construction Update
30Â November, 2025
Â
Â
We're excited to bring you this month's update at ARC Residences. Â
Â
Mostly notably this month;
Â
Level 1:Â U101 Wine room doors installed, services fit-off commenced, stone installation to bathrooms commenced.
Level 2:Â Tiling in general unit areas nearing completion, grout in bathrooms nearing completion.
Level 3:Â General unit area tile lay commencing, joinery nearing completion.
Level 4:Â Carpentry works commenced, joinery loaded in.
Level 5:Â Sheet, set & sanded.
Level 6:Â Sheet and set, waterproofing to wet areas.
Level 7:Â Rough-in partially complete.
Level 8:Â Glazing nearing completion, framing commencing.
Level 9:Â Glazing install commenced, C&P set out complete.
Level 10:Â Blockwork commenced.
Communal Roof Terrace:Â Pool springs installed.
Penthouse Roof Terrace:Â Slab poured, blockwork nearing completion, precast verticals installed.