ARC Residences Construction Update
Arc Residences, Toowong
December Construction Update
31 December, 2025
We're excited to bring you this month's update at ARC Residences.
Mostly notably this month;
- Level: Service fit off nearing completion. Stone installs to kitchen and laundry commenced.
- Level 2: Tiling in general unit areas nearing completion. Grout in bathrooms nearing completion.
- Level 3: General unit area tile lay nearing completion.
- Level 4: Joinery commenced. Tile lay to wet areas commenced. Floor prep commenced.
- Level 5: Joinery loaded.
- Level 6: Carpentry works commenced.
- Level 7: Sheet, set and sanded.
- Level 8: Sheeting commenced.
- Level 9: C&P framing commenced.
- Level 10: C&P set out commenced.
- Communal Roof Terrace: Pool sprayed.
- Penthouse Roof Terrace: Formwork stripped.