ARC Residences Construction Update
Arc Residences, Toowong
February Construction Update
27 February, 2026
We're excited to bring you this month's update at ARC Residences.
Mostly notably this month;
- Ground: Feature podium structural steel 75% installed. Lightweight framing now well underway. Lobby glazing subframe installed.
- Level 1: Defects and builders clean underway. Pool being tiled.
- Level 2: Defecting commencing.
- Level 3: Fitoff complete and carpet install beginning.
- Level 4: Fitoff commencing.
- Level 5: Corian installed.
- Level 6: Tile lay to general area commenced.
- Level 7: Joinery install commenced.
- Level 8: Joinery install underway.
- Level 9: Floor prep.
- Level 10: Sheeting complete. Glazing complete. Carpentry fix out underway.
- Private Roof Terrace: Pool spray complete. Pool tiling commencing. Glazing complete.
- Communal roof terrace: Pool rendered. Floor finishes going in. BBQ bench installed.