Glasshouse Construction Update
Glasshouse, Burleigh Heads
September Construction Update
28 September, 2023
It has been a very busy month onsite with Groupline Construction completing the upper basement level, the formwork stripping underneath, plus the ramp up to the mid basement.
The completion of the upper basement has allowed Groupline to start removing retention propping as they continue to progress the structure.
We are excited to share with you a video showing the crane being erected on site back in July.