Hampton Ltd Construction Update
Hampton Ltd, Hampton
December Construction Update
31 December, 2025
We are delighted to provide you with the monthly construction update at Hampton Ltd for December 2025.
- Structural works: Columns and Dincel walls for the Level 2 structure have been erected, reinforced, and poured. The common staircase in Building C has been installed and poured, and the roof of Building C Part 2 has been poured and completed.
- Building A works: Installation of windows has commenced, along with electrical and plumbing rough-ins.
- Basement services: Electrical rough-in has begun including cable trays. Fire services are well progressed and near completion, and Kingspan insulation installation is nearing completion.
- Building C services: Fire and mechanical rough-ins have commenced on the Ground Floor (Part 1).
- Site works: Fencing around 26 Thomas Street has been completed.