Hampton Ltd Construction Update
Hampton Ltd, Hampton
May Construction Update
3 June, 2025
We are delighted to provide you with the monthly construction update at Hampton Ltd for May 2025
Hampton Ltd has made significant progress during May, most notably;
- Steel Reinforcement delivered via crane in order to prepare the Ground Floor Slab of Building A.
- Storm Water & Sewer Penetrations completed for the Ground Floor Slab of Building A.
- Steel Reinforcement as well as Post Tensioning elements (Tendons, Grout Tubes etc) have been completed for Building A Ground Floor Slab.
- Building C: Tanks & Pits for plumbing have been excavated, reinforced and poured.
- Electrical Rough in for Building A Ground Floor Slab has been completed.
- Building A Ground Floor Slab concrete pour has been completed.
- Dincel Walls for Building A Ground Floor are in the process of being erected.
- Building B Ground Floor Slab: Steel Reinforcement, Penetrations, Electrical Rough In & Post Tensioning Elements have been completed.
- Building A Columns on Ground Floor Slab have been formed as well as steel reinforcement completed.
- Pouring of Ground Floor Slab of Building B has been completed!
- A portion of Columns & Concrete Pads for Building C's Basement have been completed.
- Currently Preparing the basement slab with crushed rock, compaction etc for Building C.