Hampton Ltd Construction Update
Hampton Ltd, Hampton
May Construction Update
31 May, 2026
We are delighted to provide you with the monthly construction update at Hampton Ltd for May 2026.
Mostly notably this month;
Plastering in Building A is nearing completion, with the majority of areas now stopped up and sanded.
Internal staircases for Apartments 207 & 208 have been installed.
Waterproofing and tiling to all wet areas in Building A are nearing completion.
Rough-in works for Building C are well underway on Levels 1 & 2.
Building B’s ground floor framing, including posis’s and lift shaft structures, has been completed.
The rooftop and terraces of Building C have been stripped and cleaned, now showcasing excellent views out to sea.
Works on the prototype/display apartment are progressing well, with joinery, flooring, tiling, and painting underway.
Hebel installation on Building A has commenced.
Metal cladding to the exterior of Building A is also underway.
Most windows in Building C have now been installed, with only a few remaining.