Level 1:Â Stone installation completed, floor coverings commencing.
Level 2:Â Joinery installation completed. Tiling completed, stone under manufacture and commenced installation.
Level 3:Â Joinery installation completed. Tiling commenced, stone under manufacture. Building external render and paint being progressed.
Level 4:Â Joinery deliveries and installation commenced, tiling commenced. Building external render and paint being progressed.
Level 5:Â Pre-paint completed, joinery under manufacture, floor levelling completed. Building external render and paint being progressed.
Level 6:Â internal framing and sheeting commenced. Building external skimming and finishing including rendering commenced. Scaffold removal commenced.
Level 7 Rooftop:Â Rooftop structure completed, rooftop services commenced. Scaffold removal commenced.
Â
Building lift installation has also commenced alongside progressing the building services works such as the main switchboard and other infrastructure.