Moray House Construction Update
Moray House, New Farm
December Construction Update
31st December, 2025
We're excited to bring you this month's update at Moray House.
Mostly notably this month;
- Level 1: final stages of internal works.
- Level 2: Stone installation commenced, building externals progressing behind scaffold, including screen track installation commenced.
- Level 3: Stone installation progressing, due for completion mid-December. building externals progressing behind scaffold, including screen track installation commenced.
- Level 4: Joinery installation being completed, stone measure completed, building externals progressing behind scaffold, including screen track installation and landscape planter boxes being filled with soil.
- Level 5: Joinery installation commenced, tiling commenced. Building externals progressing behind scaffold, including screen track installation and landscape planter boxes being filled with soil.
- Level 6: Internal sheeting being commenced and joinery procurement underway. Final drainage inspection complete. Scaffold removal commenced. External landscape planter boxes being filled with soil.
- Level 7 Rooftop: Rooftop structure completed, rooftop services being commenced. Scaffold removal commenced.