Moray House Construction Update
Moray House, New Farm
February Construction Update
27th February, 2026
We're excited to bring you this month's update at Moray House.
Mostly notably this month;
- Level 1 - Internal works - Carpentry install with skirting, door hardware, and finishing works being undertaken.
- Level 2 - Stone installation complete, timber flooring commenced, sanitary fit-off being commenced.
- Level 3 - Stone installation complete, timber floor underlays being commenced.
- Level 4 - Joinery & Stone installation completed, tiling near completion, sanitary fit-off being commenced.
- Level 5 - Joinery installation near completion, stone installation commenced, external balustrade works and scaffold removal commenced.
- Level 6 - Internal works continuing, Scaffold removal completed, Landscaping continuing. Final coats of external paint & render being completed.
- Level 7 Rooftop - Framing near completion, rooftop pool now structurally completed, plants installed, scaffold removed.
Building Lift installation continues with all lift doors in place, and commissioning taking place. Car Lift installation continues.